ELECTRICAL INSTALLATIONS OF BUILDINGS - PART 7: REQUIREMENTS FOR SPECIAL INSTALLATIONS OR LOCATIONS - SECTION 704 - CONSTRUCTION AND DEMOLITION SITE INSTALLATIONS (FIRST REVISION) (IEC 60364-7-704:1999, IDT)
This Malaysian Standard apply to temporary installations provided for:
– works of new building construction;
– works of repair, alteration, extension, or demolition of existing buildings;
– public engineering works;
– earthworks;
– and similar works.
The rules do not apply to installations covered by IEC 60621, or to other installations where equipment of a similar nature to that used in surface mining applications is involved.
Parts of buildings which undergo structural alterations, such as extension, major repair or demolition, are considered to be like construction sites during the period of relevant works, to the extent that the work necessitates the provision of a temporary installation.
For the administrative locations of construction sites (offices, cloakrooms, meeting rooms,canteens, restaurants, dormitories, toilets, etc.) the general rules of Parts 1 to 6 of IEC 60364 apply.
NOTE – For special situations, more severe requirements apply, e.g. Section 706 for restr
Published
• (none) / (none) / (none)
PDF
10/05/2019
14
NSC 05 - Generation, Transmission & Distribution of Energy